Knowledgebase: Claim Rejections
Facility NPI (Box 32A) Is Required (RC136)
Posted by Will Morrow, Last modified by Charmagne Williams on 12 May 2017 03:36 PM
Rejection: Facility NPI (Box 32A) Is Required (RC136)

What happened: The facility NPI in box 32a was not sent.

Resolution: When the facility loop is sent, the NPI is required as well. Add the NPI in box 32a and update the claim.